STREET IMPROVEMENT PROJECT
2011-2012 FISCAL YEAR
This is the
approved list of Streets to be improved starting July 2011 The total
Street Project is estimated to be in the range of $1.1m plus engineering
costs. The GRGID Board of Trustees will award this bid at their May 19, 2011
Board Meeting
Streets to be Fog Sealed
Acorn
Ann Way
Cobblestone Drive
Jill Drive
Kathy Way
Keystone Court
Kingston Ln.
Lost River Lane
Rainshadow
Rocky Terrace Dr.
Reconstruct Streets
Bowles Lane
Julie Way
Long Valley Rd. South of Jane Way
Patricia Dr. - East of Long Valley
Patricia Ct.
Slurry Seal Streets
Adeline Way
Banner Drive
Belmont Court
Birdie Court
Bobwire Ct.
Bumblebee Drive
Cahi Circle
Carmel Way
East Peak Lane
Evening Star Lane
Galena Court
Glenwood Lane
Irene Court
Keepsake Circle
Lyell Way
Maverick Court
Old Nevada Way
Palisade Circle
Ranch Drive
Ritter Way
Whitney Way
Wonder Court